Build-Out Budget
Detailed construction and renovation budget with line-item cost estimates.
1. Budget Summary
Total Build-Out Cost Estimates
| Category | Low Estimate | Mid Estimate | High Estimate |
|---|---|---|---|
| Construction | $120,000 | $150,000 | $200,000 |
| FF&E (Furniture, Fixtures, Equipment) | $25,000 | $35,000 | $50,000 |
| Permits & Fees | $3,000 | $5,000 | $8,000 |
| Professional Fees | $5,000 | $10,000 | $15,000 |
| Contingency (10%) | $15,000 | $20,000 | $27,000 |
| TOTAL BUILD-OUT | $168,000 | $220,000 | $300,000 |
Cost per Square Foot Analysis
| Estimate | Total | Square Feet | Cost/SF |
|---|---|---|---|
| Low | $168,000 | 3,500 | $48/sf |
| Mid | $220,000 | 3,500 | $63/sf |
| High | $300,000 | 3,500 | $86/sf |
Benchmark Comparison:
- General commercial tenant improvement: $100-$300/sf
- Franchise salon suites (Sola, JC): ~$224/sf
- Luxa estimate: $63/sf (Mid) - 72% below franchise cost
Cost Advantage Sources:
- China FF&E sourcing (40-60% savings on furniture)
- Owner-managed construction (potential 15-20% savings)
- Right-sized facility (3,500 sf vs larger franchise formats)
- Efficient suite mix (high Standard/Plus ratio)
2. Construction Costs Breakdown
By Trade
| Trade | % of Total | Low | Mid | High | Notes |
|---|---|---|---|---|---|
| Demolition | 3% | $3,600 | $4,500 | $6,000 | Depends on existing conditions |
| Framing/Drywall | 25% | $30,000 | $37,500 | $50,000 | STC 48-52 premium wall assembly |
| Electrical | 18% | $21,600 | $27,000 | $36,000 | 2x 20A dedicated per suite |
| Plumbing | 15% | $18,000 | $22,500 | $30,000 | 10 shampoo bowls (Plus tier+) |
| HVAC | 12% | $14,400 | $18,000 | $24,000 | Fresh air + zone control |
| Flooring | 10% | $12,000 | $15,000 | $20,000 | Premium LVP 20+ mil |
| Paint/Finishes | 7% | $8,400 | $10,500 | $14,000 | Prime + 2 coats |
| Doors/Hardware | 5% | $6,000 | $7,500 | $10,000 | 18 suite doors + common areas |
| Ceiling | 5% | $6,000 | $7,500 | $10,000 | Acoustical tile |
| TOTAL CONSTRUCTION | 100% | $120,000 | $150,000 | $200,000 |
Construction Cost Detail
Demolition ($3,600 - $6,000)
- Remove existing partitions (if any)
- Flooring removal
- Ceiling tile removal (if required)
- Haul-off and disposal
- Note: Highly dependent on existing shell condition
Framing/Drywall ($30,000 - $50,000)
STC 48-52 Wall Assembly (Premium Soundproofing):
- 3-5/8" metal studs, 24" O.C.
- R-13 insulation
- Double 5/8" drywall both sides
- Green Glue damping compound between layers
- Acoustical sealant at all perimeters
Quantity Estimates:
- Suite demising walls: ~600 linear feet
- Common area walls: ~150 linear feet
- Per linear foot: ~$40-$65 for STC 48-52 assembly
Note: Standard STC 36-40 walls would cost ~$25-$35/LF (30% savings) but compromise tenant satisfaction
Electrical ($21,600 - $36,000)
Per Suite:
- 2x 20A/120V dedicated circuits: $400-$600 per circuit
- 4-8 duplex outlets: $50-$75 each installed
- GFCI protection at wet locations
- Task lighting circuits
Common Areas:
- 200A main panel upgrade (if needed): $2,000-$4,000
- Reception, break room, laundry circuits
- Emergency lighting
- Security system circuits
Total Circuits Needed:
- 18 suites x 2 circuits = 36 dedicated suite circuits
- Common areas: ~10 circuits
- Total: ~46 circuits
Plumbing ($18,000 - $30,000)
Shampoo Bowl Installation (10 bowls for Plus tier+):
- Per bowl rough-in: $800-$1,500
- Per bowl trim-out: $200-$400
- Hot water distribution
- Drain connections (below-slab if needed)
Common Area Plumbing:
- Restroom fixtures (existing or new)
- Break room sink
- Laundry connections (washer/dryer)
Quantity:
- 10 shampoo bowls (Plus: 5, Large: 3, Executive: 2)
- 2-3 common area connections
HVAC ($14,400 - $24,000)
Requirements:
- 15-45 CFM fresh air per suite (per occupancy)
- Zone control for tenant comfort
- Exhaust for nail suite variation (if applicable)
- Quiet operation (NC 35-40 target)
Work Scope:
- Extend existing HVAC system
- Add supply diffusers (18 suites + common)
- Return air ducting (corridor)
- Thermostat/zone controls
- Balance and commissioning
Note: Major HVAC modifications (new unit) could add $10,000-$20,000
Flooring ($12,000 - $20,000)
Premium LVP Specification:
- 20+ mil wear layer
- 100% waterproof
- Commercial-grade traffic rating
- ~$4-$6/sf installed
Square Footage:
- 18 suites x ~120 sf avg = 2,160 sf
- Common areas: ~700 sf
- Corridors: ~400 sf
- Total: ~3,260 sf floored area
Paint/Finishes ($8,400 - $14,000)
Scope:
- Prime all new drywall
- 2 coats finish (eggshell)
- Neutral palette (tenant flexibility)
- Touch-up after fixture installation
Square Footage:
- Wall surface area: ~10,000-12,000 sf
- Ceiling (if painted): ~3,500 sf
Doors/Hardware ($6,000 - $10,000)
Suite Doors (18):
- 36" solid core doors: $200-$300 each
- Self-closing hardware: $50-$75 each
- Electronic smart lock prep: $50 per door
- ADA compliant
Common Area Doors:
- Entry: existing or upgrade
- Break room: 1 door
- Restrooms: 2 doors
- Storage: 1 door
Smart locks purchased separately in FF&E budget
Ceiling ($6,000 - $10,000)
Acoustical Tile:
- 2x4 lay-in tile system
- NRC 0.55+ for sound absorption
- ~$2-$3/sf installed
Scope:
- All suite ceilings
- Common area ceilings
- Grid system replacement (if needed)
3. FF&E Costs Breakdown
Detailed FF&E Budget (Implementing Split Sourcing)
| Item | Qty | Unit Cost | Total | Source | Notes |
|---|---|---|---|---|---|
| US-Sourced Items | |||||
| Shampoo bowls (backwash) | 10 | $600 | $6,000 | US (Keller) | Plumbing warranty |
| Laundry - commercial washer | 1 | $1,000 | $1,000 | US (Speed Queen) | Warranty |
| Laundry - commercial dryer | 1 | $1,000 | $1,000 | US (Speed Queen) | Warranty |
| Lighting fixtures (CRI 90+) | 50 | $100 | $5,000 | US | CRI verification |
| Access control system | 1 | $3,500 | $3,500 | US (Nexkey) | Integration/support |
| Security cameras (8-cam) | 1 | $1,600 | $1,600 | US (UniFi) | US support |
| US Subtotal | $18,100 | ||||
| China-Sourced Items | Includes 30% tariff + shipping | ||||
| Styling chairs | 18 | $250 | $4,500 | China (Hongli) | Landed cost |
| Styling mirrors | 18 | $120 | $2,160 | China (Alibaba) | Landed cost |
| Wall cabinets | 18 | $120 | $2,160 | China (Foshan) | Landed cost |
| Base cabinets | 15 | $180 | $2,700 | China (Foshan) | Landed cost |
| Carts/trolleys | 18 | $100 | $1,800 | China (Yoocell) | Landed cost |
| Reception desk | 1 | $500 | $500 | China (Custom) | Landed cost |
| Break room furniture | 1 set | $800 | $800 | China (Alibaba) | Landed cost |
| Waiting area seating | 1 set | $600 | $600 | China (Alibaba) | Landed cost |
| China Subtotal | $15,220 | ||||
| Local Items | |||||
| Exterior signage | 1 | $2,000 | $2,000 | Local | Permits may apply |
| Local Subtotal | $2,000 | ||||
| TOTAL FF&E | $35,320 |
FF&E Cost Comparison: Split Sourcing vs All-US
| Category | All-US Cost | Split Sourcing | Savings |
|---|---|---|---|
| Shampoo bowls | $6,000 | $6,000 | $0 (keep US) |
| Styling chairs | $14,400 | $4,500 | $9,900 |
| Mirrors | $5,400 | $2,160 | $3,240 |
| Cabinets (wall + base) | $9,900 | $4,860 | $5,040 |
| Carts/trolleys | $4,050 | $1,800 | $2,250 |
| Reception/furniture | $4,000 | $1,900 | $2,100 |
| Tech (access, cameras) | $5,100 | $5,100 | $0 (keep US) |
| Laundry | $2,000 | $2,000 | $0 (keep US) |
| Lighting | $5,000 | $5,000 | $0 (keep US) |
| Signage | $2,000 | $2,000 | $0 (keep local) |
| TOTAL | $57,850 | $35,320 | $22,530 (39%) |
4. Permits & Fees
| Item | Low | Mid | High | Notes |
|---|---|---|---|---|
| Tenant Improvement Permit | $2,000 | $3,000 | $4,000 | Based on construction value |
| Zoning Certificate of Use (ZCU) | $50 | $100 | $200 | Verify current fee |
| Plan Review Fees | $500 | $750 | $1,000 | Included in TI in some cases |
| Electrical Permit | Included | Included | Included | Sub-permit under TI |
| Plumbing Permit | Included | Included | Included | Sub-permit under TI |
| Mechanical Permit | Included | Included | Included | Sub-permit under TI |
| Fire Marshal Review | Included | Included | Included | Part of TI process |
| Salon Permit (VA DPOR) | $225 | $225 | $250 | State license |
| Business License (Loudoun) | $15 | $50 | $50 | County license |
| Inspection Fees | Included | Included | Included | Part of permit fees |
| TOTAL PERMITS | $2,790 | $4,125 | $5,500 |
Rounded Budget: $3,000 - $5,000 - $8,000 (includes buffer)
5. Professional Fees
| Service | Low | Mid | High | Notes |
|---|---|---|---|---|
| Architect/Space Planner | $3,000 | $6,000 | $8,000 | Required for permits |
| Permit Expediter (optional) | $0 | $1,000 | $2,000 | May save time |
| Legal (lease review) | $1,000 | $1,500 | $2,000 | Commercial RE attorney |
| Customs Broker (China) | $300 | $500 | $800 | Required for imports |
| Pre-Shipment Inspection | $300 | $400 | $600 | China QC |
| Insurance Setup | $500 | $1,000 | $1,500 | Broker fees |
| TOTAL PROFESSIONAL | $5,100 | $10,400 | $14,900 |
Rounded Budget: $5,000 - $10,000 - $15,000
6. Contingency Allocation
Contingency Rate: 10% of subtotal (standard for commercial TI)
| Subtotal | Contingency (10%) |
|---|---|
| Low ($153,000) | $15,300 |
| Mid ($200,000) | $20,000 |
| High ($273,000) | $27,300 |
Contingency Allocation by Risk Category
| Risk Category | Allocation | Purpose |
|---|---|---|
| Permit Delays | $2,000-$3,000 | Extended carrying costs |
| Change Orders | $5,000-$8,000 | Scope modifications |
| Material Price Changes | $2,000-$4,000 | Inflation, supply chain |
| Unexpected Conditions | $3,000-$6,000 | Hidden issues in space |
| China Shipping/Tariff | $2,000-$4,000 | Rate changes, delays |
| Inspection Failures | $1,000-$2,000 | Rework if needed |
| TOTAL CONTINGENCY | $15,000-$27,000 |
7. Funding Alignment (Phase 8 Reference)
Available Funding (from Phase 8 Financial Model)
| Source | Amount | Notes |
|---|---|---|
| SBA 7(a) Loan | $228,000 | Mid-range recommendation |
| Owner Equity | $57,000 | From $150K available |
| Working Capital (reserved) | $35,000 | 6-month operating buffer |
| TOTAL AVAILABLE | $320,000 | |
| Less Working Capital | ($35,000) | Reserved for operations |
| Available for Build-Out | $285,000 |
Budget vs. Funding Comparison
| Estimate | Build-Out Cost | Available | Surplus/(Gap) |
|---|---|---|---|
| Low | $168,000 | $285,000 | +$117,000 |
| Mid | $220,000 | $285,000 | +$65,000 |
| High | $300,000 | $285,000 | ($15,000) |
Conclusion: Mid estimate comfortably within funding capacity. High estimate requires minor equity increase or scope reduction.
Use of Surplus (Mid Estimate)
If build-out comes in at Mid estimate ($220,000), surplus of $65,000 could be allocated to:
| Option | Amount | Purpose |
|---|---|---|
| Increased Working Capital | $35,000 | Extended runway (12 months vs 6) |
| Enhanced FF&E | $15,000 | Premium upgrades, more shampoo bowls |
| Marketing Reserve | $10,000 | Pre-opening tenant acquisition |
| Owner Draw Reserve | $5,000 | Personal financial buffer |
8. Cost Reduction Opportunities
If budget constraints require, the following value engineering options are available:
| Opportunity | Savings | Trade-off | Recommendation |
|---|---|---|---|
| STC 45 walls vs STC 48-52 | ~$5,000-$8,000 | Slightly less soundproofing | NOT recommended (key differentiator) |
| Fewer shampoo bowls (8 vs 10) | ~$1,200-$2,000 | Shared shampoo for some Plus | Consider if tight |
| Self-manage subs vs GC | ~$20,000-$30,000 | Significant time commitment | Consider if experienced |
| More China sourcing | ~$5,000-$10,000 | Additional lead time, risk | Already optimized |
| Standard lighting vs CRI 90+ | ~$1,500-$2,500 | Color accuracy impacted | NOT recommended (tenant need) |
| Reduce contingency to 7% | ~$6,000-$8,000 | Higher risk exposure | NOT recommended |
| Phase signage | ~$1,500 | Delayed branding | Acceptable short-term |
| Standard vs premium LVP | ~$3,000-$5,000 | Durability difference | Consider if tight |
Recommended if budget tight:
- Phase signage ($1,500 savings)
- Reduce to 8 shampoo bowls ($1,200-$2,000 savings)
- Standard LVP if quality acceptable ($3,000-$5,000 savings)
Total potential savings: $5,700-$8,500 without compromising core differentiators
9. Budget Tracking Template
Use this template to track actual vs. estimated costs during build-out:
Summary Tracking
| Category | Budgeted (Mid) | Actual | Variance | Notes |
|---|---|---|---|---|
| Construction | $150,000 | $______ | $______ | |
| FF&E | $35,000 | $______ | $______ | |
| Permits & Fees | $5,000 | $______ | $______ | |
| Professional Fees | $10,000 | $______ | $______ | |
| Contingency | $20,000 | $______ | $______ | |
| TOTAL | $220,000 | $______ | $______ |
Construction Detail Tracking
| Trade | Budgeted | Bid Amount | Actual | Variance |
|---|---|---|---|---|
| Demolition | $4,500 | $______ | $______ | $______ |
| Framing/Drywall | $37,500 | $______ | $______ | $______ |
| Electrical | $27,000 | $______ | $______ | $______ |
| Plumbing | $22,500 | $______ | $______ | $______ |
| HVAC | $18,000 | $______ | $______ | $______ |
| Flooring | $15,000 | $______ | $______ | $______ |
| Paint/Finishes | $10,500 | $______ | $______ | $______ |
| Doors/Hardware | $7,500 | $______ | $______ | $______ |
| Ceiling | $7,500 | $______ | $______ | $______ |
| TOTAL | $150,000 | $______ | $______ | $______ |
FF&E Tracking
| Item | Budgeted | Order Date | Paid | Received | Actual Cost |
|---|---|---|---|---|---|
| Shampoo bowls | $6,000 | //___ | [ ] | [ ] | $______ |
| Styling chairs | $4,500 | //___ | [ ] | [ ] | $______ |
| Mirrors | $2,160 | //___ | [ ] | [ ] | $______ |
| Wall cabinets | $2,160 | //___ | [ ] | [ ] | $______ |
| Base cabinets | $2,700 | //___ | [ ] | [ ] | $______ |
| Carts/trolleys | $1,800 | //___ | [ ] | [ ] | $______ |
| Reception desk | $500 | //___ | [ ] | [ ] | $______ |
| Break room furniture | $800 | //___ | [ ] | [ ] | $______ |
| Waiting area | $600 | //___ | [ ] | [ ] | $______ |
| Washer/Dryer | $2,000 | //___ | [ ] | [ ] | $______ |
| Lighting | $5,000 | //___ | [ ] | [ ] | $______ |
| Access control | $3,500 | //___ | [ ] | [ ] | $______ |
| Cameras | $1,600 | //___ | [ ] | [ ] | $______ |
| Signage | $2,000 | //___ | [ ] | [ ] | $______ |
| TOTAL | $35,320 | $______ |
Change Order Log
| CO # | Date | Description | Amount | Approved By | Status |
|---|---|---|---|---|---|
| 001 | //___ | $______ | [ ] Approved [ ] Pending | ||
| 002 | //___ | $______ | [ ] Approved [ ] Pending | ||
| 003 | //___ | $______ | [ ] Approved [ ] Pending | ||
| TOTAL COs | $______ |
Payment Schedule Tracking
Contractor Payments (30/30/30/10):
| Milestone | % | Budgeted | Invoice Date | Paid Date | Amount |
|---|---|---|---|---|---|
| Contract signing | 30% | $45,000 | //___ | //___ | $______ |
| Rough-in complete | 30% | $45,000 | //___ | //___ | $______ |
| Substantial completion | 30% | $45,000 | //___ | //___ | $______ |
| Final/punch list | 10% | $15,000 | //___ | //___ | $______ |
| TOTAL | 100% | $150,000 | $______ |
10. Key Assumptions
This budget is based on the following assumptions. Actual costs may vary based on site-specific conditions.
| Assumption | Basis | Impact if Different |
|---|---|---|
| Shell condition | "As-is" retail space, minimal demo | +$10-20K if extensive demo needed |
| Existing HVAC | Functional system, extension only | +$15-25K if new unit required |
| Plumbing access | Above-slab preferred, below-slab possible | +$5-10K if below-slab throughout |
| Electrical capacity | 200A available or upgradeable | +$3-5K if service upgrade needed |
| Floor condition | Level, suitable for LVP | +$2-5K if leveling required |
| Ceiling height | 9-10 ft (standard retail) | Minimal impact |
| Local labor rates | Loudoun County average | Varies by contractor |
| Material costs | 2026 pricing | Subject to inflation |
| China tariffs | 30% effective rate | Budget has buffer for changes |
| Lead times | Normal shipping (45-75 days China) | Expedited shipping +$2-5K |
Build-Out Budget Estimate Complete - Phase 09-02 Task 3